1)If 9 men working 6 hours a day can do a work in 88 days. Then 6 men working 8 hours a day can do it in how many days?
(a)98 days
(b)99 days
(c)100 days
(d)102 days
2)If 34 men completed 2/5th of a work in 8 days working 9 hours a day. How many more man should be engaged to finish the rest of the work in 6 days working 9 hours a day?
(a)100 men
(b)34 men
(c)110 men
(d)120 men
3)If 5 women or 8 girls can do a work in 84 days. In how many days can 10 women and 5 girls can do the same work?
(a)32 days
(b)45 days
(c)60 days
(d)36 days
4)Worker A takes 8 hours to do a job. Worker B takes 10hours to do the same job. How long it take both A & B, working together but independently,to do the same job?
(a)20 days
(b)40/9 days
(c)9 days
(d)12 days
5)A can finish a work in 18 days and B can do the same work in half the time taken by A. Then, working together, what part of the same work they can finish in a day?
(a)1/4
(b)1/5
(c)1/8
(d)1/6
6)A is twice as good a workman as B and together they finish a piece of work in 18 days.In how many days will A alone finish the work.
(a)24
(b)27
(c)30
(d)36
7)A can do a certain work in 12 days. B is 60% more efficient than A. How many days does B alone take to do the same job?
(a)7
(b)8
(c)15
(d)15/2
8)A can do a piece of work n 7 days of 9 hours each and B alone can do it in 6 days of 7 hours each. How long will they take to do it working together 8 2/5 hours a day?
(a)3 days
(b)2 days
(c)1 days
(d)4 days
9)A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together they can finish the work in 2 days. B can do the work alone in ?
(a)6
(b)8
(c)10
(d)4
10)X can do ¼ of a work in 10 days, Y can do 40% of work in 40 days and Z can do 1/3 of work in 13 days. Who will complete the work first?
(a)x
(b)y
(c)z
(d)both x and y together
Sol1: From the above formula i.e (m1*t1/w1)=(m2*t2/w2)
so (9*6*88/1)=(6*8*d/1)
on solving, d=99 days.
Sol 2: From the above formula i.e (m1*t1/w1)=(m2*t2/w2)
so, (34*8*9/(2/5))=(x*6*9/(3/5))
so x=68 men
number of men to be added to finish the work=68-34=34 men
Sol 3: Given that 5 women is equal to 8 girls to complete a work
so, 10 women=16 girls.
Therefore 10women +5girls=16girls+5girls=21girls.
8 girls can do a work in 84 days
then 21 girls ---------------?
answer= (8*84/21)=32days.
Therefore 10 women and 5 girls can a work in 32days
Sol 4: A's one hour work=1/8.
B's one hour work=1/10
(A+B)'s one hour work=1/8+1/10 =9/40
Both A & B can finish the work in 40/9 days
Sol 5 : Given that B alone can complete the same work in days=half the time
taken by A=9days
A's one day work=1/18
B's one day work=1/9
(A+B)'s one day work=1/18+1/9=1/6
Sol 6: If A takes x days to do a work then
B takes 2x days to do the same work
=>1/x+1/2x=1/18
=>3/2x=1/18
=>x=27 days.
Hence, A alone can finish the work in 27 days.
Sol 7: Ratio of time taken by A&B=160:100 =8:5
Suppose B alone takes x days to do the job.
Then, 8:5::12:x
=> 8x=5*12
=> x=15/2 days.
Sol 8: A can complete the work in (7*9)=63 days
B can complete the work in (6*7)=42 days
=> A's one hour's work=1/63 and
B's one hour work=1/42
(A+B)'s one hour work=1/63+1/42=5/126
Therefore, Both can finish the work in 126/5 hours.
Number of days of 8 2/5 hours each=(126*5/(5*42))=3days
Sol9: Suppose A,B and C take x,x/2 and x/3 hours respectively finish the
work then 1/x+2/x+3/x=1/2
=> 6/x=1/2
=>x=12
So, B takes 6 hours to finish the work.
Sol 10: Whole work will be done by X in 10*4=40 days.
Whole work will be done by Y in (40*100/40)=100 days.
Whole work will be done by Z in (13*3)=39 days
Therefore,Z will complete the work first.